Port of Gdynia: EU projects
Infrastructure of road and railway access to the Eastern part of Port of Gdynia
(Former title: Construction of Port Infrastructure for servicing Sea-Ferries together with the road and railway access in Port of Gdynia)



I. Project description


Project Infrastructure of road and railway access to the Eastern part of Port of Gdynia consists of two stages:

Stage I: The Road Access
Stage II: The Railway Access with road elements

Stage I is to be realized by:

- Reconstruction and extension of Polska Street (construction of a new roadway and 4 crossings) from roundabout named "December 70' Victims" to the crossing with Chrzanowskiego Street, with the reconstruction of the underground infrastructure and rail crossings;
- Reconstruction of Chrzanowskiego and Wendy streets in the existing road lane, on the length from the crossing with Polska Street to the railway flyover;
- Partial reconstruction of Celna Street along the length from the crossing with Polska Street to the rail crossing;
- Construction of a car-park for trucks at Chrzanowskiego Street with the social-office building;
- Construction of personal car-park at Chrzanowskiego Street and the other at Polska Street.

Stage II realizing by:

- Reconstruction of railway tracks along the length from flyover in Solidarnosc Alley to the area of the roundabout between Polska Street and Chrzanowskiego Street;
- Construction of the road - railway surface from the rail crossing in Rotterdamska Street to the area of the roundabout with Chrzanowskiego Street;
- Additional reconstruction of Polska Street on the length from the roundabout with Chrzanowskiego Street to Marine Station with Gombrowicza Square;
- Construction of a car - park for trucks at Polska Street;
- Construction of a personal car - park at Celna Street

Within the whole investment the demolition of several buildings will be necessary.

II. The project objective


The project realization will improve the road and railway access to terminals in the Eastern part of Port of Gdynia. Polska Street, Chrzanowskiego Street and Wendy Street road line makes a part of Gdynia communication system related to VI Transport Corridor of TEN-T net and will link the east area of Port with the motorway A1. Polska Street is an element that is necessary in assurance of an easy, quick and efficient road access to the Port Gdynia. It extends two-lane roads route leading to the Port, including Tricity Ring-Road, Kwiatkowskiego Flyover, Wiśniewskiego and Polska streets. The road is an important element of an access to a new Ferry Terminal which is planned in the future at Polish and Finnish quays, making a main traffic route in the eastern part of Port of Gdynia.

Then, the reconstruction of a railway structure will improve a railway access to terminals situated at Polish Quay and will allow to conduct rail wagons un/loading by a heavy port equipment, which will enable transhipment in intermodal systems.

An effect of the project realization will be mainly an increase of the capacity of the road and railway systems both. Furthermore, it will intensify a fluency of a road traffic and improve its safety. Technically the road surface will have a greater bearing capacity. It also meaningly will increase the number of parking places for trucks waiting for a port service and for personal cars.

This investment relates directly also to Motorways of the Sea programme as well as to the Short Sea Shipping. It was found as a priority in the INTERREG III programme where it received the subsidy for the preliminary concept and feasibility study (SEBTrans-Link Project, 2005).

III. European Union Funds


This investment is featured, with the "key project" status, with the number POIiS 7.2 - 2, in the indicative projects list for Operational Programme - Infrastructure and Environment 2007 - 2013, Priority Axis no. VII - Environment-Friendly Transport, Activity no. 7.2 Development of Sea Transport.

IV. Basic Technical Data


New roads: 2.400 lm
Reconstructed roads: 2.000 lm
Crossings: 5
Road - railway surface: 12.600 m2
Modernized railway tracks: 2.700 lm
Car-parks for trucks: 2 (29.300 m2)
Car - parks for personal cars: 3 (5.800 m2)

V. Activities for investment realization


The work schedule assumes the construction of the road access during 2008 - 2010 and of the railway access (with the road elements) during 2010 - 2011.

According to the detailed schedule for construction works, planned termination of the works in Stage I had to come till June 2010 and then construction works of Stage II had to start. However works have come much earlier, in December 2009.

Technical acceptance of executed Stage I of investment took place on December 29th 2009. By the end of May 2009 the advancement of works came to 76,6 %. Until now Polska Street has been expanded into another dual carriageway, situated behind warehouses of the second zone of Polskie Quay. Four crossings and roundabouts has been reconstructed and the construction of car park for trucks at Chrzanowskiego Street has been completed. This car - park, holding over 130 trucks, has been already given into use in May 2009. The construction design respecting of Stage II of project realization was accepted in August 2009 and after this the application for a construction permission was placed. However, getting of the construction permission will extend because of formal reasons.

Dates of activities, preparing of documents and obtaining of decisions:

No.Task descriptionCommencement date
month/year
Completion date
month/year
1.Designing Works03'200408'2009
2.Construction permission
Stage I
Stage II

03'2006
03'2010

03'2006
05'2010
3.Application Works01'201007'2010
4.Tender documentation
Stage I - road access
Stage II - railway access

03'2007
05'2010

12'2007
06'2010
5.Announcement of the tender
Stage I
Stage II

12'2007
07'2010

12'2007
07'2010
6.Offers preparation
Stage I
Stage II

01'2008
07'2010

02'2008
09'2010
7.Offers assessment and acceptance of the tender results
Stage I
Stage II

04'2008
10'2010

04'2008
10'2010
8.Signing of the contract with the contractor
Stage I
Stage II

05'2008
11'2010

05'2008
11'2010
9.Construction works
Stage I
Stage II

05'2008
12'2010

12'2009
12'2011


Questions may be directed to: spoleczne.polska@port.gdynia.pl